A lot of activity continues on the main campus Progress: -Tennis Courts nearing completion with an all new look-Stage floor getting final coats of paint-Steel beams, roofing and brick laying taking place on Fine Arts addition-Ground has been broken for greenhouse -Restroom/Changing room makeover in Fine Arts area continues You can view an on-going archive of photos fr...
Continue reading
  153 Hits
  0 Comments
153 Hits
0 Comments

June starts with a lot of activity

June has started with a lot of activity.  Paving, pool and auditorium demolition, main gym work, track and tennis resurfacing, etc.  The campus is tacking on a construction zone theme but so far everyone has cooperated and activities have ran smoothly. Progress: -Paving-Pool, auditorium, track, gym demolition-Tennis resurfacing You can view an on-going archive of...
Continue reading
  192 Hits
  0 Comments
192 Hits
0 Comments

Steady Progress During May

Construction move forward steadily during the month of May.  Beginning June 1 the pool and auditorium will begin with demolition work.  Following the SDHS graduation black top begins on campus with various phases taking place through the month of June.  The work in the main gym begins June 7.  Track and tennis court begins in June along with constructio...
Continue reading
  188 Hits
  0 Comments
188 Hits
0 Comments

Construction Progress!

Construction progress continues on a number of areas. Progress: -High School chillers close to completion-Access Road sees a lot of dirt being moved-Work started on new parking area by soccer field-Fine Arts addition is progressing nicely You can view an on-going archive of photos from this project in the Photo Archive.
  494 Hits
  0 Comments
494 Hits
0 Comments

Breaking Ground

IMG-1635
Our construction project is finally started. You can view an on-going archive of photos from this project in the Photo Archive